M5 East Motorway

Project Works – AUGUST 2015 – Cooks River Tunnel Resheeting

The Cooks River Tunnel’s road surface was re-sheeted during the August closure period, covering a total length of almost 500 metres of motorway. Approximately 460 tonnes of asphalt was applied. The process was conducted over 4 night shifts and included milling of the existing asphalt surface, re-sheeting with new asphalt, and line-marking. You can watch footage of the works conducted here: